Talking Points for the Nadu Nedu Webinar Meeting on 23-July-2020

Talking Points for the Nadu Nedu Webinar Meeting on 23-July-2020
నాడు-నేడు వీడియో కాన్ఫరెన్స్ విశేషాలు
1. Water Quality Test at RWS labs should be taken for all schools and Should be Uploaded in CRP login APP. (R2.4 Report is for Monitoring)
2. Some schools were facing issues in Working Estimates amount Reduction ,It was discussed and Option will be Enabled.
3. Working Estimates Can be less than Admin sanction Amount. But Overall amount should not be less than Expenditure Amount Paid to School.
4. All Schools should Raise Central Procurement Indents as per the Requirement , HMs will not be allowed to Raise Expenditure bills if Central Procurement Indents are not Raised.
5. Option for Pull Back/Editing of furniture indents in HMs Login and Sanitary ware ,Painting in FE login from 23 July 00:00:00 Hours to 25th July 2020 12:00:00 Hours Only.
6. PCs Decision is final in deciding Rates . Mandal Engineers can Advice but cannot object the decision. If rates are higher it should given on Paper.
7. All 9 Components should be taken Up . Mandal Engineer should accept works based on requirements and needs given by PCs and to be included in working Estimates.
8. For Demo Schools Central Procurement Indents Payments will be done directly to Vendor. For all Non Demo Schools Payments to the Supplied Quantity will be done through CFMS.
9. Provision to Upload and acknowledge Central Procured Invoices will be Given in Mobile APP .
10. Any Surplus / Unused Materials Can be sold to Another Schools on Cost Basis only after Resolution of Parents Committees.
11. Some schools Received Revolving Fund but fund Not utilized due to Various Reasons . A Government Account Details will be given for Refunding Excess Amount back to Treasury.
12.Blank Cheques Leaves / Vouchers/Minutes are being signed in Advance by PCs/FE. This should be Avoided.
13.Engineering assistants not entering data in Work Measurements books . All EE should give Mbooks to Engineering assistants for Recording all work Progress.
14. Honorable CM has extended the target Date of Completion to End of August 2020.
15. Don’t Engage Contractors unless permission is Obtained from Commissioner School Education . It is Punishable if Contractors are engaged without Permission
16.All HMs Should visit Mana Badi Nadu Nedu Website http://nadunedu.se.ap.gov.in/stmsworks/ and view HM Documents Section.
17.Handwritten Bills/Vouchers Uploaded in Portal but Materials not found in Work Location(Ex. 20MM Metal,WPC Doors) but Issuing Cheques to Vendors.In this case disciplinary Action Will be Initiated
18.Handwritten Bills/Vouchers Uploaded in Portal but Materials is not present in Work Location , Cheques are also not issued. Only Uploaded for showing Progress of works.
19.Bills/Vouchers are attested by only HMS. Bills /Vouchers should be attested by HM and at least one PC Member also.
20.Many Schools are not Maintaining/Using Brands as Specified in GO / Circular given by Government while buying TubeLights,Wires ,Steel,Tiles etc .
21.Register Entry is not Updated Regularly by Schools by HMs.
22.Most of the Parents Committees are not aware of the Works done in the Schools.
23.Weekly Meetings are Not being conducted in Schools
24.100% schools will be taken up for Social Audit . If discrepancies found disciplinary action will be taken against Concerned Officials.
25.Some HM are writing Self Cheques for more than 10000/-
26.For Purpose of Showing Expenditure Bogus Bills are Uploaded
27.Some Materials Are Purchased for Higher rate – Bill amount is different from Actual Payment Amount
28.For Entire Mandal , Materials are bought from same Shops but Variations in bills prices Across Schools